Advertisement
Management

Earned Value Analysis for Project Performance in Project Cost Management

Every stakeholder is concerned about project costs. The ability to accurately forecast project performance in terms of costs and schedule is a powerful tool in project cost management. In this article, Project Performance formulae, such as estimate at completion and estimate to complete are shown.

By Rupen Sharma, PMP
Desk Management
Reading time 5 min read
Word count 879
Monitoring and controlling the project Project management
Earned Value Analysis for Project Performance in Project Cost Management
Advertisement
Quick Take

Every stakeholder is concerned about project costs. The ability to accurately forecast project performance in terms of costs and schedule is a powerful tool in project cost management. In this article, Project Performance formulae, such as estimate at completion and estimate to complete are shown.

On this page

Introduction to Earned Value Project Performance Formulae

Earned Value is a part of the Project Cost Management knowledge area. This is the last in the series of articles on Earned Value computations. The other articles in this series are:

To gauge project performance by using Earned Value Analysis formulae, use the following:

Advertisement
  • Estimate at Completion (EAC): Computes project performance by looking at the total cost of the project when it is completed based on the current rate of progress.
  • Estimate to Complete (ETC): Calculates project performance by looking at the amount of money required to complete the project based on the current rate of progress.
  • Variance at Completion (VAC): Computes project performance by looking at the variance of the total project cost at completion when compared with the project budget.
  • To-Complete Performance Index (TCPI) based on BAC: Represents the level of project performance that future project work needs to be implemented to meet the budget.
  • TCPI based on EAC: Represents the level of project performance that future project work needs to be implemented to meet the project’s cost based on past project performance.

Next, let’s look at a couple of examples to compute project performance.

Example 1

Suppose you have a budgeted cost of a project at $900,000. The project is to be completed in 9 months. After a month, you have completed 10 percent of the project at a total expense of $100,000. The planned completion should have been 15 percent. Now, let’s see the project performance.

Advertisement

From the scenario, you can extract the following project performance parameters:

  • BAC = $900,000
  • AC = $100,000

The project performance in terms of Planned Value and Earned Value can then be computed as follows:

Advertisement
  • Planned Value = Planned Completion (%) * BAC = 15% * $900,000 = $135,000
  • Earned Value = Actual Completion (%) * BAC = 10% * $900,000 = $90,000
  • Cost Performance Index = EV / AC = $90,000 / $100,000 = 0.90

The Earned Value Project Performance formulae are as follows:

  • Estimate at Completion (EAC) = BAC / CPI = $900,000 / 0.9 = $1,000,000. At the current rate, the project performance in terms of cost is: Project completion in $1,000,000 as opposed to a planned budget of $900,000.
  • Estimate to Complete (ETC) = EAC – AC = $1,000,000 - $100,000 = $900,000. If the project performance continues at this rate, the project requires $ 900,000 to be completed.
  • Variance at Completion (VAC) = BAC – EAC = $900,000 - $1,000,000 = - $100,000. The project will be $100,000 over-budget at completion. The project will run $100,000 over-budget at completion.
  • To-Complete Performance Index (TCPI) based on BAC = (BAC – EV) / (BAC – AC) = ($900,000 - $90,000) / ($900,000 - $100,000) = $810,000 / $800,000 = 1.01
  • TCPI based on EAC = (BAC – EV) / (EAC – AC) = ($900,000 - $90,000) / ($1,000,000 - $100,000) = $810,000 / $900,000 = 0.9

Note: Read the Protect Your Project Against Cost Overruns article to understand how to use buffers.

Advertisement

Example 2

Suppose you are managing a software development project. The project is expected to be completed in 8 months at a cost of $10,000 per month. After 2 months, you realize that the project is 30 percent completed at a cost of $40,000. You need to determine whether the project is on-time and on-budget after 2 months. Let’s see the project performance.

Step 1: Calculate the Planned Value (PV) and Earned Value (EV)

Advertisement

From the scenario, you can extract the following project performance parameters:

  • Budget at Completion (BAC) = $10,000 * 8 = $80,000
  • Actual Cost (AC) = $40,000
  • Planned Completion = 2/8 = 25%
  • Actual Completion = 30%

Therefore, the project performance in terms of Planned Value, Earned Value, and Cost Performance Index is:

Advertisement
  • Planned Value = Planned Completion (%) * BAC = 25% * $80,000 = $20,000
  • Earned Value = Actual Completion (%) * BAC = 30 % * $80,000 = $24,000
  • Cost Performance Index = EV / AC = $24,000 / $40,000 = 0.6

The Earned Value Project Performance formulae are as follows:

  • Estimate at Completion (EAC) = BAC / CPI = $80,000 / 0.6 = $133,333. At the current rate, the project performance will be such that it will be completed with $133,333 as opposed to a planned budget of $80,000.
  • Estimate to Complete (ETC) = EAC – AC = $133,333 - $40,000 = $93,333. Project performance at this rate means that the project requires $93,333 to be completed.
  • Variance at Completion (VAC) = BAC – EAC = $80,000 - $133,333 = -$53,333. The project performance in terms of budget will be: $53,333 over-budget at completion.
  • To-Complete Performance Index (TCPI) based on BAC = (BAC – EV) / (BAC – AC) = ($80,000 - $24,000) / ($80,000 - $40,000) = $56,000 / $40,000 = 1.4
  • TCPI based on EAC = (BAC – EV) / (EAC – AC) = = ($80,000 - $24,000) / ($133,333 - $40,000) = $56,000 / $93,333 = 0.6

Following the golden rules for managing risk and scope creep will get the project back on-track.

Advertisement
Keep Exploring

More from Management

Filed under
Monitoring and controlling the project
More topics
Project management
Advertisement